Tanahun Hydropower Project achieves 78 percent physical progress

1 min read 19 reads
Tanahun Hydropower Project achieves 78 percent physical progress
Photo credit: Khabarhub

DAMAULI: Physical progress on the 140-MW Tanahun Hydropower Project has reached 78 percent, with construction advancing across all three packages of the project in Jhaputar, Rishing Rural Municipality-1, Tanahun.

Project Chief Shyamji Bhandari said work is progressing significantly under all three packages. Package 1 covers the dam and other headworks, Package 2 includes the main tunnel, powerhouse and related equipment, while Package 3 involves construction of the Damauli-Bharatpur 220-kV transmission line.

Under Package 1, the dam and other headworks are being constructed by Songda Kalika JV. Physical progress under the package has reached 63 percent, Bhandari said. Construction of the main dam, access road, temporary dam for diverting the Seti River and two diversion tunnels has been completed.

Originally published by Khabarhub on Oct 8, 2026 Read the full article at english.khabarhub.com
Read original
About this page. The Ditible is an aggregator. This article was imported from a publisher feed and may have been reformatted. Copyright remains with the original publisher, and the headline, image and any quoted text are used for attribution and indexing purposes. Source links are preserved on every item in the archive.
Share

Comments

0 comments

psst, say something nice 💬

No comments yet Be the first to say something. Go on, it is quiet in here.
more from

Khabarhub

View source
you might like

Up next