- Islamabad: Pakistan is facing a massive trade deficit of $40.5 billion while 40 major power transmission projects financed through foreign loans are struggling with funding delays, government approvals, land access problems and security concerns, the National Assembly Standing Committee on Economic Affairs Division was informed.
- The committee was told that the 40 ongoing projects cover six major categories of work, including improvements to the transmission and distribution system, construction and upgrading of grid stations, the CASA 1000 transmission project and other infrastructure needed to strengthen Pakistan’s electricity network.
- The committee was informed that several problems are slowing down the work, including delays in government approvals, No Objection Certificates, land access and coordination between federal and provincial authorities.
AI Generated Summary
Islamabad: Pakistan is facing a massive trade deficit of $40.5 billion while 40 major power transmission projects financed through foreign loans are struggling with funding delays, government approvals, land access problems and security concerns, the National Assembly Standing Committee on Economic Affairs Division was informed.
The committee was told that Pakistan imported goods worth $80.9 billion during the financial year 2025 to 2026, compared with exports of only $40.4 billion. The figures showed that the country spent almost twice as much on imports as it earned from exports, raising serious questions about its ability to reduce dependence on foreign borrowing.
The meeting was held at Parliament House, Islamabad, under the acting chairmanship of Dr. Mirza Ikhtiar Baig, MNA. According to the briefing, 40 ongoing power transmission projects are being financed by international development partners under 17 loan agreements. However, only about 52 percent of the total agreed loan amount has been disbursed so far.
The committee was informed that delays in the allocation of rupee cover, which is the local currency funding needed to use foreign loans, have become a major obstacle to project implementation. These delays have affected the timely release and use of loan funds and the settlement of payments according to approved project schedules.
The projects are being supported by the World Bank, Asian Development Bank, Agence Française de Développement, KfW Development Bank and Japan International Cooperation Agency. The committee was told that the 40 ongoing projects cover six major categories of work, including improvements to the transmission and distribution system, construction and upgrading of grid stations, the CASA 1000 transmission project and other infrastructure needed to strengthen Pakistan’s electricity network.